Southbank, Victoria

The Problem


Staff at this global manufacturing company had nowhere to charge their electric vehicles at their head office in Southbank, Melbourne. 


They approached ChargeHub for the infrastructure solution and ChargeHub approached Quality Energy to install the EV chargers.


Challenges were many and included working with the Building Manager to obtain approval for the installation, ensuring the switchboard had the electrical capacity to support powering the EV chargers, working outside office hours to minimise disruption to all tenants in the building and avoiding peak traffic periods, then running the cabling in a straight route from the level 8 tenancy switchboard to the car park on the ground floor.


For insurance and safety purposes, the client requested integration into the fire system after the chargers were installed. This was done through a shunt trip relay that trips in the event of a fire.

The Solution

Quality Energy installed 3 x AC 22kW EVBox BusinessLine EV chargers in the car park on the ground floor at Freshwater Place and connected them to the ChargeHub software.

Benefits and Outcomes

Key equipment

3 x AC 22kW EVBox BusinessLine EV Chargers, manufactured in the Netherlands

System size

3 x AC 22kW

Project warranty

2-years

Let's talk about your project

Contact us or call 1800 736 374 to talk about how we can help your business improve energy efficiency and reduce your energy cost.

Is your business suffering from unexplained electrical faults, failures or power spikes?

A power quality audit will identify issues and give us the data we need to design an appropriate solution for your business. 

Contact us
Share by:
..... ..... .....
..... ..... .....
...... ......