Parkville, Victoria

The Problem


When CitiPower/Powercor moved to a kVA network tariff for medium to large business customers, the University of Melbourne's electricity bills increased significantly. Their inefficient electrical systems and poor power factor meant that when their demand for electricity was high, they were charged for that peak demand portion across the year.


They invited Quality Energy to tender for the installation of Power Factor Correction equipment to improve their power factor and increase efficiencies in the electrical systems.

The Solution

After an extensive tender process, Quality Energy were awarded the contract to design, manufacture and install 26 low voltage Power Factor Correction (PFC) units.


The PFCs ranged from 62.5kVAr through to 400kVAr and were installed at locations identified as running with poor power factor.

Benefits and Outcomes

Key equipment

26 x Quality Energy customised Power Factor Correction units

System size

26 x PFC units totalling 4,387kVAr

Project warranty

3-years

Let's talk about your project

Contact us or call 1800 736 374 to talk about how we can help your business improve energy efficiency and reduce your energy cost.

Is your business suffering from unexplained electrical faults, failures or power spikes?

A power quality audit will identify issues and give us the data we need to design an appropriate solution for your business. 

Contact us
Share by:
..... ..... .....
..... ..... .....
...... ......